The 6-Step Procurement Checklist
-
Step 1: Confirm the exact Allen-Bradley PLC model and part number
-
Step 2: Map out programming software and certification needs
-
Step 3: Build a total-cost checklist with hidden lines
-
Step 4: Inspect the electrical system around the PLC
-
Step 5: Plan commissioning and the fault reset sequence
-
Step 6: Know when not to buy Allen-Bradley
-
Step 1: Confirm the exact Allen-Bradley PLC model and part number
-
Common Mistakes and Final Notes
If you're replacing an Allen-Bradley PLC or adding one to an electrical project, this checklist is for you. I'm the procurement manager who signs off on controls and power equipment, and over the years I've learned that the lowest quote can be the most expensive one. This list keeps our upgrades from turning into budget overruns.
Use this when you know the machine you're equipping. It works for a new Allen-Bradley Micro850 on a small conveyor, a CompactLogix upgrade on a packaging line, or a full system with a Cummins 1500 kW diesel generator and a smart panel. It is not a guide for comparing every brand in the market. I'll point out when Allen-Bradley isn't the right fit at the end.
The 6-Step Procurement Checklist
Step 1: Confirm the exact Allen-Bradley PLC model and part number
When I first started buying controls, I assumed 'Allen-Bradley PLC' meant one product. What I mean is, I treated it like a commodity. That's wrong. The Allen-Bradley 850 PLC, officially Micro850, is part of the Micro800 family and uses Connected Components Workbench software (Source: Rockwell Automation, rockwellautomation.com, accessed January 2025). A CompactLogix or ControlLogix system is a completely different platform with different software, wiring, and spare parts.
Before you get a quote, write down:
- Exact catalog number and controller series (for example, 2080-LC50-24QWB)
- Current firmware revision needed by the existing HMI or SCADA
- I/O mix: digital, analog, thermocouple, high-speed counter
- Communication requirements: Ethernet/IP, serial, device-level ring
Put another way: if you order by 'same PLC as last time' without checking the part number, you can end up with the right package and the wrong I/O density. Oh, and verify whether the part is still active or going obsolete. We lost a week once to a discontinued module that looked identical in the catalog.
Step 2: Map out programming software and certification needs
Software is often a bigger line item than the controller itself. Micro800 controllers use Connected Components Workbench; Logix controllers use Studio 5000. If your team needs formal training, look at the Allen-Bradley PLC programming certification path in Rockwell Automation's training catalog. As of January 2025, Rockwell lists classroom and self-paced courses for both platforms (Source: Rockwell Automation, rockwellautomation.com).
Add these to the project budget, not to next year's training wishlist:
- Software license and version level
- Number of programmer seats
- Controller emulation tools if you plan to test off-line
- Certification exam fees and travel
I should add that certification is not just a resume perk. If your in-house team can't interpret a fault code or upload a program, the commissioning cost will eat any savings from buying the 'value' PLC.
Step 3: Build a total-cost checklist with hidden lines
The base quote is only the beginning. Let me rephrase that: the base quote is the cover charge; the total cost is the bar tab. Include cabling, terminal blocks, Ethernet switch ports, spare fuses, programming cables, spare I/O modules, and a secure place for the program backup.
We didn't have a formal quote-comparison checklist when I started. The third time we missed a programming cable, I made a one-page spreadsheet. Every vendor quote now has to line up with 15 checkboxes. That change alone saved us about $8,400 in change orders in the first year, which is roughly 17% of our annual controls parts budget.
For a Micro850 or any fixed-I/O controller, order at least one spare unit if the machine is critical. For a larger system, order spare output modules and one communication module. Store them with the archived program, not in a different building.
Step 4: Inspect the electrical system around the PLC
This is the step most people skip until startup. A PLC is only as reliable as the power feeding it, and the PLC is part of a larger circuit that includes the generator, transfer switch, distribution panel, and grounding system.
If the site needs 1.5 MW of backup capacity, a Cummins 1500 kW diesel generator is a common spec. Check current datasheets because kW rating alone doesn't tell you about fuel consumption, starting current capability, or enclosure requirements (Source: Cummins, cummins.com, accessed January 2025).
On the distribution side, a Span electrical panel can simplify load management and generator interlocking. But it has to be configured for the exact generator output. If the panel is set up wrong, the PLC will see voltage dips during transfer and can fault for no obvious reason. Verify the transfer sequence with the panel manufacturer before you commission.
Step 5: Plan commissioning and the fault reset sequence
Write the startup procedure before you power the PLC. Check all wire terminations, ground continuity, and polarity. Then test the power sources in stages.
On a diesel generator project, know how to reset fuel pump relay before you blame the PLC. The general procedure is:
- Turn the generator control switch to OFF.
- Wait two minutes, then cycle the battery disconnect switch.
- Check the fuel pump relay coil for power and contacts for continuity.
- If the relay trips after a start attempt, replace it. Resetting isn't repairing.
The exact relay location and test voltages are in the unit's service manual. So glad I insisted on a generator load test before commissioning last year—we found a fuel pump relay that would not latch. Almost skipped that test to save a day, and it would have failed during the first real outage.
Step 6: Know when not to buy Allen-Bradley
Here's the honest limitation. Allen-Bradley is not the best fit for every project. If you have no existing Rockwell installed base, no in-house programming experience, and the machine can run on simple relay logic, you may be better off with a less expensive controller. If this is a one-off machine with short expected life, the premium is hard to justify.
In most existing plants I work with—where technicians already know the platform, spares are on the shelf, and equipment life is measured in years—Allen-Bradley is a reasonable default. 'Reasonable default' is not the same as 'always right.' Use the TCO, not the logo, to make the call.
Common Mistakes and Final Notes
The most frustrating part of PLC procurement is that the same issues reappear because people treat the PLC as the whole project. You'd think one parts list would prevent it, but the integration details are where budgets go to die.
- Ignoring firmware compatibility with existing HMI and SCADA
- Ordering a controller without software license seats
- Forgetting spare modules and program backups
- Skipping generator load testing until an outage happens
- Not defining the fuel pump relay reset process for maintenance staff
Bottom line: use a checklist, verify every line item, and recommend honestly. A good purchase decision is one that still looks smart after startup, when the machine is running and no one is signing emergency change orders.